Kerr Lake Regional Water Raw Water Facility

For the City of Henderson, Thalle installed a new raw water intake line to the existing water facility which services 50,000 customers.

The project called for the installation of 2,700 feet of 24 inch DIP and 200 feet of 36” PCCP which was installed beneath 40 feet of water in Kerr Lake. The project also called for the installation of three new raw water pumps and the associated mechanical piping. Also included in the project was a new high service pump and variable frequency drive, a new emergency generator, various electrical improvements, and associated HVAC improvements.